Glenbrook High School District 225

Glenbrook High School District 225, serving approximately 5,000 students in Glenview and Northbrook, IL, is comprised of two facilities, Glenbrook North and Glenbrook South. This project consisted of implementing storage+solar project at each of the schools: Two Tesla Megapack 2XL batteries providing 1,958.4kW/7,833.6 kWh and a 220kW solar array at the North campus and one Tesla Megapack 2XL battery providing 979kW 3,916kWh and a 190kW solar array at the South campus.

Project Details

Type: Education

Scope: North campus: Two Tesla Megapack 2XL batteries providing 1,958.4kW / 7,833.6 kWh and a 220kW Solar Array

South campus: One Tesla Megapack 2XL battery providing 979kW / 3,916kWh and a 190kW Solar Array

Utility Company: ComEd

Locations: Glenview/Northbrook, Illinois

Completion: 2026

 